Status of pending application
Name of region Rewa Report for Quarter ending Sept-05
(B) Where  extension work is required
S. No. Category No.of application pending as at the end of month Agewise break up  Resons for pending
Less then one month 1 to 3 month 3 to 6 months More then 6 months For want of formalities by consumer For want of inspection by licensee For want of sanction by licensee For want of issue of demand note by licensee For want of installation of meter and release of connection Any other reason
L.T. Connections
1 Domestic 17 5 3 0 9 8 0 0 0 0 9
2 Non domestic 9 4 1 0 4 5 0 0 0 0 4
3 Industrial 13 2 2 0 9 3 0 0 0 0 10
4 Agricultural Pump 10870 0 0 0 10870 0 0 0 0 0 10870
5 Others 643 0 0 0 643 2 0 0 0 0 641
6 Total 11552 11 6 0 11535 18 0 0 0 0 11534
H.T. Connections   9 1 1 1 6 4 0 0 0 5 0