Status of pending application
Name of region Rewa Report for Quarter ending Sept-05
(A) Where no extension work is required
S. No. Category No.of application pending as at the end of month Agewise break up  Resons for pending
Less then one month 1 to 3 month 3 to 6 months More then 6 months For want of formalities by consumer For want of inspection by licensee For want of sanction by licensee For want of issue of demand note by licensee For want of installation of meter and release of connection Any other reason
L.T. Connections
1 Domestic 203 203 0 0 0 131 20 0 13 39 0
2 Non domestic 33 33 0 0 0 12 2 0 0 19 0
3 Industrial 31 31 0 0 0 11 0 18 0 2 0
4 Agricultural Pump 11 11 0 0 0 7 0 4 0 0 0
5 Others 17 0 17 0 0 17 0 0 0 0 0
6 Total 295 278 17 0 0 178 22 22 13 60 0
H.T. Connections   0 0 0 0 0 0 0 0 0 0 0